Paymentology Key Guide
Paymentology key guide helps you as a client to understand the keys involved in a project when setting up with a Card Manufacturer. It helps provide the timelines for each key and will help guide when keys will be generated and shared respectively.
We recommend that as soon as a project is opened with the Card Manufacturer, that Paymentology Card Programme Team should be looped into an email by the Paymentology Project Manager. This way we can start the initial discussions required to kick off the project.
As some keys take some time due to PCI Compliance, we suggest that we start with the key exchange as the first activity and work in parallel on other items required.
Please see below a table for each key and the timelines. The Paymentology Card Programme Team will discuss with the Card Manufacturer on which keys will be involved and how keys will be shared. Once this is confirmed, we will then move forward in generating the keys and sharing them with the Card Manufacturer.
The Card Programme Team will work directly with the Card Manufacturer on all key activities. The Card Manufacturer should share a project plan with you as the client and keep you up to date on all aspects of the project.
ZCMK - Transport Keys >> 2 Courier Process
| Task | Projected Timeline |
|---|---|
| Card Programme Team requests for ZCMK | |
| Security Officers generate ZCMK components | 3 days |
| Day 1: Security Officers ship ZCMK component 1 >> DHL (Delivery time included) | 3 days |
| Day 2: Security Officers ship ZCMK component 2 >> FedEx (Delivery time included) | 5 days |
| Day 3: Security Officers ship ZCMK component 3 >> DHL (Delivery time included) | 3 days |
| Card Manufacturer loads components on HSM | 7 days |
| Card Manufacturer confirms KCV with Card Programme Team | 1 day |
ZCMK - Transport Keys >> Components received first process
| Task | Projected Timeline |
|---|---|
| Card Programme Team requests for ZCMK | |
| Security Officers generate ZCMK components | 3 days |
| Day 1: Security Officers ship ZCMK component 1 >> DHL (Delivery time included) | 3 days |
| Card Manufacturer confirms receipt of component 1 | 1 day |
| Day 2: Security Officers ship ZCMK component 2 >> FedEx (Delivery time included) | 5 days |
| Card Manufacturer confirms receipt of component 2 | 1 day |
| Day 3: Security Officers ship ZCMK component 3 >> DHL (Delivery time included) | 3 days |
| Card Manufacturer loads components on HSM | 7 days |
| Card Manufacturer confirms KCV with Card Programme Team | 1 day |
IMK/ MDK and PPK Key Exchange
| Task | Projected Timeline |
|---|---|
| Card Programme Team requests for IMK/MDK/PPK | |
| Security Officers generates the keys encrypting with ZCMK and PGP | 7 days |
| Security Officers share encrypted keys with Card Programme Team | 3 days |
| Card Programme Team Shares encrypted keys with Card Manufacturer | 1 day |
| Card Manufacturer loads keys and confirms KCV | 4 days |
Disclaimer: Should a card scheme share keys with Paymentology, the timeline maybe be slightly different.